This amended transformation plan sets out Dorset Council’s approach to change and aligns our newly developed transformation themes to the corporate plan.
It describes the aims, objectives and approaches to deliver these themes including the initially identified key projects that support their delivery.
The overarching aim of this amended approach is to build on our one council approach and the learning and opportunities COVID-19 has enabled, as well as the financial challenges it has presented us with.
The Dorset Council Plan sets out our vision, values and our organisational aspirations.
Our transformational approach must support us to bring these to life and shape our services and together with our organisational principles of being customer focused, effective and modern, an employer of choice and creating a sustainable organisation this transformation plan will enable the new Dorset Council to continue to make those a reality.
Our vision:
To make Dorset a great place to live, work and visit.
Our values:
It is important to describe what an organisation will be like once transformation aspirations have been realised.
In bringing the elements together from the Dorset plan and refining them, our aim is that the transformed council will:
There is a huge degree of uncertainty about the future state of public finances following COVID-19.
Initial modelling suggests an anticipated budget gap in 2021/22 of £41.9 million. Inaction is therefore not an option and this amended transformation plan takes into consideration both the increased emphasis on transforming services to save money and the greater amount required from change activities in order to bridge the budget gap.
In order to respond to the financial challenges, whilst still delivering our vision and values according to our principles, the council has agreed five transformation themes to guide our journey towards the kind of council we want to become.
These are to:
The following sections set out these themes in more detail and describe how they support the council to deliver on its values, describes the approaches required to deliver them, who needs to be involved and how the changes will be monitored and managed.
This theme delivers on the following Council Plan Values:
The aim of this theme is to transform the council’s approach in order to play an important role in place shaping in Dorset, to support the delivery of the economic development strategy and outcomes from COVID recovery.
Working with partners to understand and tackle longer-term health and wellbeing improvements including people of Dorset having good quality jobs, homes and strong social networks. We want to focus on outcomes, for example, community wealth building approaches as an additional economic recovery measure and enabling a nuanced approach across the county to meet local need.
The council wants to be a key player in place shaping in order to:
In order to deliver our aspirations, the council will adopt a co-production approach.
Taking a strengths/assets based approach to community development, facilitating community led responses and the importance of connecting people to their communities. Providing infrastructure support to anchor organisations/community leaders to lead community support.
Adopting this approach to stimulate Dorset’s economy as it recovers from the impacts of COVID alongside a strong economic development strategy and vision for digital which includes facilitating the delivery of digital infrastructure and other key enablers will significantly contribute to making Dorset a great place to live work and visit. We will put people and communities at the heart of the change we are creating.
This is about leading with a shared sense of purpose and clarity of outcomes and repurpose activity in order to deliver these outcomes.
This theme delivers on the following Council Plan Values:
To make Dorset an inclusive county focused on helping people at the earliest point.
The outcomes we want to achieve from this theme are:
The approach to this theme is to collate data and information and analyse the impact of the current approaches and how these need to change.
We will analyse where we spend our revenue across pathways and services to get the balance right between supportive interventions and early preventative interventions.
This will enable us to understand and evidence the cost of outcomes in Dorset.
Often the approach to wait for a crisis or for problems to hit an eligibility threshold mean services are more expensive to deliver.
In order to act, we will use data to inform our decisions as well as learning from others, before delivering a comprehensive programme of change.
This theme delivers on our principles of being effective and modern and the following Council Plan Values:
The aim of this theme is to create and operationalise a robust approach to asset, estate and capital management.
The outcomes we want to achieve from this theme are and asset, estate and capital management strategy and embedded approach that supports the council to:
Capital strategy and asset management group (CSAMG) will lead this theme.
The group will review existing approaches and support the development of these where they do not currently exist and then subsequently bring these together aligned to the budget setting process.
Once the strategy is in place processes and procedures can be established to embed and operationalise good asset management practice and transformation to the council’s estate to deliver revenue savings.
This theme delivers on the following Council Plan values:
The aim of this theme is to reduce the operating cost of the council by adopting a robust approach to service reviews by embedding a service design approach to examining alternative delivery models including co-production or more efficient ways of delivering services while maximising income.
The service design approach is well established way to examine options and redesign services in a customer focussed way.
Together with the approach to value for money reviews agreed by Cabinet in October 2020 this will make sure the council systematically benchmarks and assesses its service provision against others.
Services are stopped, re-imagined, reshaped, or enhanced and enabled through the use of technology and data to reduce operating costs or improve income.
Improve service offerings by utilising data and continually measuring services.
Starting with services that have a significant budget or that could generate more income, systematically use the service design approach to implement the new customer service approach and review services examining alternative delivery models and methods, including options to reduce service quality in order to generate savings.
This would include robust financial understanding of the existing services, any future options proposed and the cost to implement the changes.
The approach would include benchmarking our services against comparator organisations to understand our balance of cost and quality and finding out if we are offering more or less than we need to.
To do this we will ask and challenge ourselves to think differently.
The long term benefits of adopting this approach will be to move towards delivering proactive services rather than reacting to an issue, maintaining control of the services we need to provide, which in turn will move us away from the need to 're-design' and embed a culture of ‘just keep designing'.
This theme delivers on all our Council Plan values:
The aim of this theme is through our approach to transformation and other specific actions, to create an organisation that is an employer of choice.
The outcomes of this theme are to:
This theme is strongly underpinned by the council’s people strategy, including work programmes within Organisational Development to support the development of great leadership and an inclusive culture together with deliver of the outcomes in the Dorset Workplace.
How an organisation embarks on transformation at this scale can have a positive or negative impact on culture depending on the approaches taken.
The success of the transformation programme will be supported through work to develop the organisational approach to leadership and culture.
This work will highlight the journey that employees will take as we continue to embed the new culture for Dorset Council.
Work is taking place with managers to lead the way in embracing change, committing to our new shared ways of working and language, and leading in our behaviours.
This work will align to the People Strategy and the Dorset Workplace within the broader Council Plan and will help empower employees to work more efficiently and embrace best practice, whilst having their holistic needs met.
It will enable all employees to build better relationships and be a part of the changes, on our journey to become an employer of choice. During the council’s response to the COVID-19 pandemic we adopted different techniques for driving change.
This included investment and energy from across the whole workforce who stepped forward and were redeployed.
Our delivery at pace during this time has been because we have moved to a more positive risk-taking framework and in order to deliver the transformation we aspire to, we need to keep this momentum and enable many more people to participate in delivery and this refreshed transformation plan enables that to happen, through the new approach to governance described in the next sections.
Alongside the desire to progress transformation plans differently is the additional financial challenges on the council as a result of COVID-19.
With a £41.9 million projected budget gap for 2021/22, transformation must deliver more and deliver it quickly.
Therefore, the currently identified transformation projects (described below) while supporting the delivery of our transformation themes also contribute considerably to supporting the council to bridge the deficit.
It is anticipated that as projects that support the delivery of our transformation themes come forward they will be prioritised and added to the portfolio and savings totals updated.
Working on a rolling basis with projects coming forward throughout the year should encourage the whole organisation to always be thinking about alternative more effective ways to do things and plan in the delivery of those projects.
Year 1, 2021 to 2022 - £9158057.00
Year 2, 2022 to 2023 - £8740525.00
Year 3 to 5, 2023 to 2025 - £6500000
Grand total £24398582.00
Year 1, 2021 to 2022 - £6581922.00
Year 2, 2022 to 2023 - £6035525.00
Year 3 to 5, 2023 to 2025 - £3000000.00
Grand total £15617447.00
Year 1, 2021 to 2022 - £1070000.00
Year 2, 2022 to 2023 - £2125000.00
Year 3 to 5, 2023 to 2025 - £3500000.00
Grand total £6695000.00
Year 1, 2021 to 2022 - £1616135.00
Year 2, 2022 to 2023 - £580000.00
Year 3 to 5, 2023 to 2025 - £0
Grand total £2096135.00
As described above, in addition to the savings above, there are new projects currently in early stages of initiation, with the scope to make further savings. Discovery work is underway enabling the total value of savings to be clearer in the next 4-6 weeks. It is expected these will identify several million in further savings
When the transformation programme was first conceived there was a transformation fund of £5million established to support the investment required to deliver change.
In line with Cabinets decision in Nov 2019 allocations from the fund (detailed below) have been over seen by the transformation board and followed a gateway process and the criteria set out for the transformation fund.
In line with the revised approach to transformation it is recommended to Cabinet that the Performance Leadership Group take on the responsibility of allocating and keeping track of the fund.
A revised gateway process is shown below demonstrating this proposed change.
It is not proposed that the investment fund criteria are changed and remain as follows. Successful applications to the fund must:
a) Deliver the priorities for Dorset Council
b) Fundamentally change systems, processes, people or technology across the whole organisation to improve outcomes for residents
c) Be able to deliver the proposal straight-away
d) Be costed and financially viable
e) Demonstrate cross-council working
f) Evidence the rational using robust data and customer insight/research
The information below demonstrates the value of the gateway process as some projects have not been taken forward to gateway 1 as initial work has led to a change of direction or emphasis or indeed the project was no longer seen to be viable as conceived.
These fund where unspent are then returned to the fund.
Currently there are 3 projects at gateway 1 and a further 7 projects proceeding, having received gateway 2 funding.
There is a further description of all projects comprising the transformation plan in the next section some of which will be looking to secure investment from the fund in order to start to deliver their outcomes.
Stage 1, not on track
Approval at gateway 1 - £40082.00
Approval at gateway 2 - n/a
Total approved spend - £40082.00
This project will improve the user experience for adults and children booking and using transport in Dorset including the provision of SEND transport through an alternative delivery model.
It will balance the travel budget and make savings by delivering a safe, reliable and compliant transport service alongside improving data quality and understanding of the true cost of the service.
Stage - 1, more information being provided before full approval can be considered
Approval at gateway 1 - £40082.00
Approval at gateway 2 - n/a
Total approved spend - £40082.00
This project will improve the user experience for adults and children booking and using transport in Dorset including the provision of SEND transport through an alternative delivery model.
It will balance the travel budget and make savings by delivering a safe, reliable and compliant transport service alongside improving data quality and understanding of the true cost of the service.
Stage - Spent
Approval at gateway 1 - £40082.00
Approval at gateway 2 - n/a
Total approved spend - £40082.00
Dorset Council is reviewing its estate following local government reorganisation to ensure assets are most effectively used or are carefully disposed of.
This includes a review of the office estate as a dependency with the Dorset Workplace programme.
Stage - 2. Bid approved
Approval at gateway 1 - n/a
Approval at gateway 2 - £1122682.00
Total approved spend - £1122682.00
This project will converge planning systems following local government reorganisation.
This will include the introduction of a single planning software system to replace the six legacy systems currently in use.
Stage - 1. more information being provided before full approval can be considered
Approval at gateway 1 - £40082.00
Approval at gateway 2 - n/a
Total approved spend - £40082.00
Following local government reorganisation, Dorset Council has inherited a number of different business solutions.
This project will implement a single cloud-based solution for regulatory services which will enable officers to work in an agile way in the community to better meet the needs of customers.
Stage - 2. Bid approved
Approval at gateway 1 - n/a
Approval at gateway 2 - £65000.00
Total approved spend - £65000.00
To equip DWP vehicles with digital devices to improve efficiency and effectiveness of service delivery.
Stage - 2. Bid approved
Approval at gateway 1 - n/a
Approval at gateway 2 - £65000.00
Total approved spend - £65000.00
This funding is to support the green premium’ associated with this initiative.
Stage - 2. Bid approved
Approval at gateway 1 - n/a
Approval at gateway 2 - £450000
Total approved spend - £450000
Through rationalising the way customer services are delivered, we will improve our overall service, reduce the cost of customer services and free up resources to support impactful services.
This includes procurement of a new digital platform to support this across the organisation.
Stage - 2. Bid approved
Approval at gateway 1 - £40082.00
Approval at gateway 2 - £220000.00
Total approved spend - £260082.00
The purpose of this project is to further develop our own data warehouse and technical skills in house to deliver transformational business intelligence, insight and performance for Dorset Council.
This will support any requirement to link into wider initiatives such as the Dorset Insight and Dorset Intelligence and Insight Service, and the Dorset Care Record.
Stage - Closed
Approval at gateway 1 - n/a
Approval at gateway 2 - n/a
Total approved spend - n/a
This project will not progress to gateway 2 and has been closed.
Stage - Closed
Approval at gateway 1 - n/a
Approval at gateway 2 - n/a
Total approved spend - n/a
This project will not progress to gateway 2 and has been closed.
Stage - 2. Bid approved
Approval at gateway 1 - n/a
Approval at gateway 2 - £160000.00
Total approved spend - £160000.00
The project will offer travel skills to young people with SEND to give young people greater independence and confidence by offering them a lifelong skill to travel independently on public transport.
Stage - Closed
Approval at gateway 1 - n/a
Approval at gateway 2 - n/a
Total approved spend - n/a
n/a
Stage - Closed
Approval at gateway 1 - n/a
Approval at gateway 2 - n/a
Total approved spend - n/a
This project has been funded from an alternative source.
Stage - 2. Bid approved
Approval at gateway 1 - n/a
Approval at gateway 2 - £285000.00
Total approved spend - £285000.00
Digital infrastructure projects to accelerate economic recovery from the impact of the coronavirus pandemic.
Stage - 1. more information being provided before full approval can be considered
Approval at gateway 1 - £50000.00
Approval at gateway 2 - n/a
Total approved spend - £50000.00
This bid is to support the entire transformation programme in adults releasing £15,617,447 of saving individual projects are listed in the next section.
Approval at gateway 1 - £210328.00
Approval at gateway 2 - £2479965.00
Total approved spend - ££2690293.00
This bid is to support the entire transformation programme in adults releasing £15,617,447 of saving individual projects are listed in the next section.
This will see Dorset Council work in partnership with Dorset schools to seek to strengthen their capacity to deliver outcomes, to redefine a new operating model, to support schools become self-sustaining and reduce reliance.
We would seek to ensure that we have the capacity in our special school system to provide support to Dorset schools across the full spectrum of needs for children with Special Educational Needs and Disability (SEND).
The project will develop a multi-purpose site to enable local provision of special schools and alternative provision.
This will tackle financial pressures on the high needs block and support the development of more appropriate provision that can meet needs and support targeted interventions.
This project will further develop a service and culture that supports whole family safeguarding, focused on meeting the needs of both children and the adults around them. By working with multidisciplinary teams, which include adult specialist workers, families can access tailored support to address their needs and the risks posed to children.
This project will redesign transactional processes to introduce self-service service portals and standardised and automated working processes and technological solutions that are fit for purpose.
This will reduce costly and inefficient workarounds, releasing efficiencies, but also change the nature of support services.
Review of early help services to ensure appropriate provision, including the role of Children’s Centres.
This project will reprofile the spend on external placements for existing children in care to ensure value for money and improve outcomes for children and young people.
This project will review the landscape in respect of unregistered provision and to implement changes to increase registered provision in Dorset, reducing cost pressures.
This project will bring children’s services and adult services together to consider the potential for a whole life service, supporting families together to improve outcomes.
This project reshapes the community offer to residents with enhanced strength-based services and enables a reduction in residential spend.
This will include reviewing out of county placements and changing the model of care homes to provide more specialist and enhanced provision.
This project will increase the number of users in receipt of direct payments by 50%. It will develop a tool to enable a review of current 700 Direct Payment Users and ensure that their payments are appropriate.
The project will explore new models of delivery for day services, including the private day services market, using learning from the Covid-19 pandemic.
Focus will be on connecting to communities, promoting wellbeing, increasing independence, pathways to employment and implementing the dementia services review.
This work will implement a process from April 2021 to charge people who use our services the actual cost of care.
This project will integrate brokerage and quality services into a joint integrated service across the Integrated Care System (ICS) footprint.
Exploration of opportunities to ensure more effective delivery of statutory services using the learning from Covid and the impact of the new service model.
Following the impact of the new service model, opportunity to reduce contracted capacity within the market
This project will explore the reduction in mileage travelled by employees for work purposes and consider the right energy efficient vehicles to reduce both cost and CO2 emissions.
This will be undertaken whilst still ensuring that we provide the same or an improved user experience for Dorset Council residents.
The harmonisation of parking charges across the Dorset Council area will be undertaken following local government reorganisation in 2019.
This will deliver greater consistency for our customers, from aligned charging and opening times across the Dorset Council car park estate.
A review of the Dorset waste service has been commissioned to benchmark Dorset against other local authorities and against the private sector.
It will make recommendations on opportunities for improved service delivery, alternative delivery models, efficiencies and financial savings.
This review will consider the leisure services offer and make recommendations in respect of future delivery models.
This programme will review the ways of working for office based employees and implement a flexible, more agile approach.
This work has a dependency with the asset management review of the Dorset Council estate.
This project will develop four aspects of commercialisation; making money, commissioning, being business friendly, and behaving in a more business like way.
The initial priority will be to focus on contract management, and identify any areas of duplication inherited from predecessor councils along with the identification of efficiencies.
This will enable contract disposal/harmonisation opportunities and savings, including effective commercial contract management and re-procurement.
Recognising that there are change or transformation resources embedded across the council that can be used to succeed in delivering a single transformation programme and to embed our #oneteam approach, a cross-organisational group called DART (Dorset Agile Resource Transformation) brings change resources and activity together across directorates and services into one place.
DART is led by Steve Ford, Corporate Director TIDE • Transformation, Innovation & Digital and Ecology.
This team will support and monitor all change whether through large projects or transformations through ongoing incremental continuous improvement that is agile.
Therefore, the delivery of change activity happens within services, by people who know and understand the business and their customers.
Our transformation themes and framework through DART reflects, supports and aids the delivery of directorate transformation plans, for example ‘A better life’ in Adult services.
Therefore, all transformation is supported by the Digital and Change Service who provide specific skills in delivering change, will co-ordinate sourcing additional capacity if needed and who will maintain the master list of changes that comprise the transformation portfolio.
They will work alongside colleagues from across the organisation to make sure EQIAs are completed early for all projects and provide a central reporting mechanism to track progress.
While DART members will work day-to-day with their project sponsors, the group as a whole and the transformation programme are directed by the Corporate Leadership Team, consisting of membership from directors and other senior leaders.
This group have accountability for the delivery of projects as business owners.
The Performance Leadership Group consists of Cabinet members and the senior leadership team and their role is to hold the programme accountable for delivery.
Subject to Cabinet’s agreement this group also determine investment in transformation and provide challenge to ensure return on investment.
Finally, project
CRR01
Budget
In order to implement transformation continued use of the transformation fund will be needed
High
CRR21
Covid-19 response
Uncertainty over our required future responses to Covid-19 will have a continued impact to the future design and delivery of transformation and the projects and programmes that comprise them
High
CRR01
Budget
Transformation has a major role to play in redesigning services in order to facilitate savings.
High
CRR021
Covid-19 response
Performance Leadership and CLT will actively review the impact of COVID-19 on phases of transformation and monitor and review impacts and priorities as necessary
High
This policy was last reviewed in 2020.
The next expected review date is autumn 2025 in line with the review and refresh of the council plan.