This document gives notice that Dorset Council has determined to make relief for exceptional circumstances available from (ADD DATE) , in accordance with Regulations 55, 56 & 57 of the Community Infrastructure Levy (CIL) Regulations 2010 (as amended).
The exceptional circumstances relief policy is intended for use solely in the area covered by the Purbeck Local Plan (2018-2034), Adopted (ADD DATE)
Applications for exceptional circumstances relief can only be submitted for planning permissions granted for specific sites listed under Local Plan Policy V1: Spatial strategy for sustainable communities, as follows:
1.a Local Plan allocated sites:
1.c Neighbourhood Plan sites of around 50 dwellings that are required to provide Habitat Regulations mitigation in accordance with Local Plan Policies E7, E8 & E9.
2. Extra care facilities at Wool and Moreton Station / Redbridge Pit, as detailed in Local Plan Policies H2, H4 & H5.
The permissions must comply with the details and requirements set out in the following relevant Local Plan housing polices:
Notwithstanding the above policy requirements, the proposals must also comply with the associated requirements for development, adopted in the Purbeck Local Plan (2018-2034), plus local and national planning policies.
The CIL rate payable for each claim will be determined in accordance with the economic viability assessment of the chargeable development.
The assessment will be undertaken by an independent person on behalf of the claimant, whose selection is with the agreement of the council.
A claim for exceptional circumstances relief can only be granted if one or more planning obligations under section 106, Town & Country Planning Act 1990 have been secured in respect to the planning permission and development.
The claim must be submitted by a person (the claimant), who is an owner of a material interest in the relevant land.
The claim must be submitted in writing on the Exceptional Circumstances Relief Claim Form, available from the Planning Portal Download the forms webpage, and be received before commencement of the development.
The claim form must be fully completed to be a valid claim and be accompanied by the following:
The claim will lapse if development is commenced before the claimant has received a decision on the claim or one or more of the following disqualifying events occur:
Please refer to the regulations 55, 56 & 57, plus legislative amendments for full details on the procedures and requirements for exceptional circumstances relief.
All claims and queries should be sent to cil@dorsetcouncil.gov.uk
This policy was last reviewed in 2024.
The next expected review date is 2025.